Progress is described on the construction of infrastructure and plant systems, and on the manufacturing of the ITER tokamak components and their assembly since the IAEA FEC 2018. Major achievements in this period have been the completion of the tokamak building and installation of the cryostat base and lower section that mark the start of tokamak assembly in 2020. This has been followed by the arrival of key core tokamak components to enable assembly of the first tokamak sector, which is made up of one vacuum vessel (VV) sector, 2 toroidal field (TF) coils and the corresponding thermal shield (TS), and the completion of manufacturing and testing of the first two poloidal field (PF) coils (PF5 and PF6). In parallel with this, the tools required for assembly have been commissioned and plant systems required for operations have progressed in construction and have started or will start commissioning in the near future. The remaining core tokamak components (e.g. the remaining eight VV sectors, TF coils, PF coils and central solenoid (CS) modules) are in advanced manufacturing state or already completed and under testing, as required for the assembly plan to first plasma (FP). In parallel with machine assembly, systems to support plasma operation during the FP and later phases of the ITER research plan (IRP) have made significant progress as well. This includes the plasma control system, for which the final design for FP has been completed, the electron cyclotron heating (ECH) system, diagnostic systems, plasma protection components for FP and the disruption mitigation system (DMS). The IRP itself has also been consolidated and specific issues identified where R&D support by the ITER Members' fusion communities may refine it further. The consolidation of the IRP has involved changes to the upgrade paths considered in the baseline by the identification of MHD stable plasma scenarios that can meet ITER's Q = 5 steady-state fusion power goal with neutral beam heating (NBI) and ECH thus removing the need for the installation of a lower hybrid current drive (LHCD) system previously included as an upgrade in the baseline for this specific purpose.
IAEA FEC 2018以降のITERトカマク構成部品の製造と組立、ならびにインフラストラクチャーおよびプラントシステムの建設に関する進捗について報告する。この期間における主要な成果は、トカマク建屋の完成と、2020年のトカマク組立開始を示すクライオスタットベースおよび下部セクションの設置である。これに続き、最初のトカマクセクター(1基の真空容器(VV)セクター、2基のトロイダル磁場(TF)コイル、および対応する熱シールド(TS)から構成される)の組立を可能にする主要なコアトカマク構成部品の到着、ならびに最初の2基のポロイダル磁場(PF)コイル(PF5およびPF6)の製造と試験の完了が達成された。これと並行して、組立に必要なツールの試運転が完了し、運転に必要なプラントシステムは建設が進み、近い将来に試運転を開始するか、すでに開始している。残りのコアトカマク構成部品(例えば、残り8基のVVセクター、TFコイル、PFコイル、および中心ソレノイド(CS)モジュール)は、先進的な製造段階にあるか、すでに完成して試験中であり、ファーストプラズマ(FP)までの組立計画に必要な状態にある。機械組立と並行して、FPおよびITER研究計画(IRP)の後期段階におけるプラズマ運転を支援するシステムも大幅に進展した。これには、FP向けの最終設計が完了したプラズマ制御システム、電子サイクロトロン加熱(ECH)システム、計測システム、FP向けプラズマ保護構成部品、およびディスラプション緩和システム(DMS)が含まれる。IRP自体も統合・整理され、ITERメンバーの核融合コミュニティによるR&D支援がさらに改良を加える可能性がある特定の課題が特定された。IRPの統合には、ベースラインで検討されていたアップグレード経路の変更が含まれており、中性粒子ビーム加熱(NBI)およびECHによってITERのQ = 5定常状態核融合出力目標を達成できるMHD安定プラズマシナリオが特定されたことにより、この特定の目的のためにベースラインにアップグレードとして含まれていた低域混成波電流駆動(LHCD)システムの設置の必要性が排除された。