This paper overviews the achievements and plans of the JT-60SA project which has been implemented jointly by Europe and Japan since 2007, covering the objectives, performance, schedule, design and procurement activities and on-site preparations. Re-baselining of the project was completed in late 2008. All of the scientific missions are preserved with the newly designed machine to meet the cost objectives. The construction of the JT-60SA has begun with procurement activities for components of the toroidal field magnet, poloidal field magnet, vacuum vessel, in-vessel components, cryostat, power supplies in parallel with dismantling the JT-60 facilities, at the end of which the first plasma is foreseen in 2016. For exploitation, development of the JT-60SA research plan has been started jointly between Japan and Europe.
本論文は、2007年以降日本と欧州が共同で実施してきたJT-60SAプロジェクトの成果と計画を概説するものであり、目標、性能、スケジュール、設計・調達活動、現地準備作業を対象としている。プロジェクトの再ベースライン化は2008年末に完了した。新設計の装置によって科学的使命のすべてが維持される。JT-60SAの建設は、トロイダル磁場コイル、ポロイダル磁場コイル、真空容器、容器内機器、クライオスタット、電源系統などの構成機器の調達活動とともに開始された。JT-60施設の解体は2016年末までに完了し、初プラズマが予定されている。一方、JT-60SAの研究計画の策定は日本と欧州が共同で開始している。